01 · Total or last row
Twelve rows contain 14, 18, 22,… lights. Find the final row and total number.
Hint
Calculate u₁₂ first, then S₁₂.
Worked solution
Final row: 14 + 11(4) = 58 lights. Total: 12(14 + 58)/2 = 432 lights.
Understand · explore · practise
Use arithmetic and geometric series for totals, budgets, capped growth, bouncing distances and regular payments. Learn payment timing with a manual model and worked practice.
Before you startArithmetic and geometric sums, sum to infinity and logarithms
01 / What quantity must be added?
If uₙ is the distance travelled on day n, then Sₙ = u₁ + u₂ + … + uₙ is the distance travelled over the first n days. The question “how far on day 8?” asks for u₈; “how far by the end of day 8?” asks for S₈.
Write the first few amounts actually being added. Their units and dates often reveal a wrong first term, a missing journey or an extra interest period before any algebra is needed.
02 / Totals with a fixed increase
u₁₅ = 18 + 14(3) = 60
This is the number in the last row.
S₁₅ = 15(18 + 60)/2 = 585
The average of first and last, multiplied by the number of rows, gives the total.
Sₙ = n[60 + 5(n − 1)]/2 = 5n(n + 11)/2
The budget applies to the cumulative cost.
S₉ = £450; S₁₀ = £525
All costs are positive, so these adjacent checks identify the last affordable month.
Nine whole months are affordable
There is £50 left, less than the £75 tenth-month cost.
If the terms can be negative, a cumulative sum need not increase; adjacent checks alone then need a separate monotonicity argument.
03 / Add a capped sequence in parts
Years 1–8 are 240, 275,…, 485
Year 9 is the first capped year: its uncapped prediction is 520.
S₈ = 8(240 + 485)/2 = 2900
Use an arithmetic sum for the uncapped years.
Years 9–12 contribute 4 × 500 = 2000
Count the capped years inclusively.
Total = 2900 + 2000 = 4900 items
The cap is included once for each of the last four years.
Using one arithmetic formula for all 12 years would count output the cap forbids. Writing the two index ranges prevents an omitted or double-counted boundary year.
04 / Totals with a fixed percentage increase
uₙ = 20(1.1)^(n − 1)
This describes the planned distance on one day.
Sₙ = 20[(1.1)ⁿ − 1]/0.1
This describes the planned total after n complete days.
S₇ = 189.74342 km; S₈ = 228.717762 km
Keep full precision until the final result.
A percentage increase in daily distance does not mean the cumulative total itself grows by that same percentage each day. Derive the sum from the individual terms.
05 / Stop when the target is reached
S₇ < 220 ≤ S₈
The target is reached during day 8.
Final-day distance = 220 − S₇ = 30.25658 km
Only the remaining distance is needed, not the full planned day-8 amount.
Day 7 distance = 20(1.1)⁶ = 35.43122 km
The earlier full-day distances increase.
The greatest actual daily distance is on day 7
Its 35.43122 km exceeds the shortened final day’s 30.25658 km.
“Eight days are needed” means seven full planned days plus part of the eighth here. A fraction of a day requires an extra speed or within-day pacing assumption; the daily sequence alone does not determine it.
06 / Bounce heights and total distance
Rebound n reaches hₙ = 6(0.6)ⁿ
The initial drop is not a rebound. The fourth rebound reaches 0.7776 m.
The sixth ground impact follows five complete rebounds
The initial drop ends at impact 1.
Distance = 6 + 2[6(0.6) + … + 6(0.6)⁵]
Count the initial drop once and each completed rebound twice.
= 6 + 12(0.6)[1 − (0.6)⁵]/(1 − 0.6) = 22.60032 m
The last rebound counted is number 5.
To ground impact k: D = H + 2Hr(1 − r^(k − 1))/(1 − r)
Infinite idealised travel: D∞ = H + 2Hr/(1 − r), for 0 < r < 1
Here the idealised infinite distance is 24 m. If the endpoint is the top of a rebound, its final upward journey is counted only once. Real balls eventually stop bouncing, so the infinite result belongs to the idealised model.
07 / Payments at the end of each year
The first deposit earns five years’ interest; the last earns none
List the contribution of each payment at the same final date.
Balance = 250(1.04)⁵ + 250(1.04)⁴ + … + 250
In increasing powers, this is a geometric series with first term 250.
= 250[(1.04)⁶ − 1]/0.04 = £1658.24
Round the final sum, not each intermediate power.
End-year payments P, multiplier r, n years:
Bₙ = P(rⁿ − 1)/(r − 1), for r ≠ 1
This model assumes a constant rate, no fees or withdrawals and no intermediate rounding. When r = 1, there is no interest and the balance is simply nP.
Pay £100 every year. Value the balance at the end of the final year, after that year’s interest and any end-year payment.
Four end-year payments total £431.01 at the end of year 4.
Paid in: £400.00. Interest: £31.01.
Bars compare the final contribution of each payment on a shared scale. Calculations retain full precision until the final total is rounded. Individual rows are displayed to the nearest penny, so their rounded sum may differ by a penny.
Pause, replay or seek freely. The notes explain the same idea and stay in view.
08 / Payments at the start of each year
The first payment earns six years’ interest; the last earns one
The payment dates have moved one year earlier.
Balance = 250(1.04)⁶ + … + 250(1.04)
There is no term with exponent zero.
= 1.04 × 250[(1.04)⁶ − 1]/0.04 = £1724.57
Multiply the unrounded end-payment expression by 1.04.
Start-year payments, valued at the final year-end:
Bₙ = Pr(rⁿ − 1)/(r − 1), for r ≠ 1
If valuation is immediately after the last start-year payment instead, the exponents are n − 1 through 0. The date of valuation matters as much as the payment label.
09 / When will regular payments reach a target?
Bₙ = 200(1.05)[(1.05)ⁿ − 1]/0.05
The latest payment earns one year of interest.
(1.05)ⁿ ≥ 1 + 2900(0.05)/[200(1.05)]
Rearrange before taking logarithms.
n ≥ 10.7606, so test n = 11
The first candidate whole year is obtained by rounding upward.
B₁₀ ≈ £2641.36; B₁₁ ≈ £2983.43
Year 11 is the first qualifying year-end.
With end-year payments instead, B₁₁ ≈ £2841.36, so year 11 would still fall short. Do not use the wrong timing formula merely because both questions mention the same annual payment.
10 / Your turn
Twelve rows contain 14, 18, 22,… lights. Find the final row and total number.
Calculate u₁₂ first, then S₁₂.
Final row: 14 + 11(4) = 58 lights. Total: 12(14 + 58)/2 = 432 lights.
Monthly costs are £20, £26, £32,… . How many complete months can a £400 budget cover?
The sum must be at most £400.
Sₙ = n[40 + 6(n − 1)]/2 = 3n² + 17n. S₉ = 396 and S₁₀ = 470, so nine months. Positive costs make later totals larger.
Annual output is min(150 + 40(n − 1), 400). Find the total over 10 years.
Seven years are uncapped, three are capped.
Year 7 gives 390; year 8 reaches the 400 cap. Total = 7(150 + 390)/2 + 3(400) = 3090 items.
A 15 km first-day plan rises by 20% daily. Stop after 140 km. Find the last day’s actual distance and the greatest actual daily distance.
Compare the remaining distance with the preceding full day.
S₅ = 111.624 and S₆ = 148.9488, so day 6 covers 140 − 111.624 = 28.376 km. Day 5 covers 15(1.2)⁴ = 31.104 km, which is the greatest actual daily distance.
A ball is dropped from 8 m and rebounds to half the preceding height each time. Find the third rebound height.
The first rebound is 4 m.
8(½)³ = 1 m.
For the same 8 m ball, find total distance up to the fifth ground impact and the infinite modelled distance.
Impact 1 is the initial drop; four rebounds are completed by impact 5.
To impact 5: 8 + 2(4 + 2 + 1 + ½) = 23 m. Infinite distance: 8 + 2[4/(1 − ½)] = 24 m.
Pay £100 at the end of each year for three years, at 10% annual interest. Value immediately after the third payment.
The powers of 1.1 are 2, 1 and 0.
100[(1.1)² + 1.1 + 1] = £331.00.
Move those three payments to the start of each year. Value at the end of year 3.
Each payment now receives one extra interest period.
100[(1.1)³ + (1.1)² + 1.1] = £364.10.
Pay £150 annually for eight years, with no interest and no withdrawals. What is the final balance?
The r = 1 case does not require a fraction.
8 × 150 = £1200. The expressions with denominator r − 1 cannot be substituted directly at r = 1.
Pay P at each year-start for n years at multiplier r. Write the balance immediately after the last payment, before the final year’s interest.
The most recent payment has exponent zero at this date.
Balance = P[r^(n − 1) + … + r + 1] = P(rⁿ − 1)/(r − 1) for r ≠ 1, or nP when r = 1. The different valuation date removes the extra factor r.
11 / Recap
Section 1 of 11 · What quantity must be added?